Project Management Professional (PMP) — Question 420

A human resource (HR) acquisition process for a large project has recently changed. One major process change includes the approval of the financial manager and the recruitment manager. This change to the process implies longer processing. The project urgently needs new resources.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because assessing the impact of the process change is crucial for understanding how it affects the project's timeline and resources. The other options do not address the need to evaluate the situation and adapt the project management plan accordingly, which is essential in urgent scenarios.