Project Management Professional (PMP) — Question 409

A project manager is leading a strategic and competitive advantage project for a healthcare organization that is in its testing phase. The team has been working on this project for 6 months, and the morale of the team is low due to the schedule.
What can the project manager do to motivate the team?

Answer options

Correct answer: D

Explanation

The correct answer, D, is effective because recognizing team members and providing incentives can significantly enhance morale and motivation. Options A and B do not directly address team morale and may not have a lasting positive impact, while option C, while beneficial, does not provide immediate recognition or reward for the team's hard work.