Project Management Professional (PMP) — Question 408
A project development team is located in different areas around the world. Last week, a very important release was delayed because one of the developers did not respond on time to an email that was sent to everyone. The developer seems to have missed reading the email.
What should the project manager do to avoid these situations?
Answer options
- A. Review the stakeholder engagement plan.
- B. Review the resource management plan.
- C. Review the risk management plan.
- D. Review the communications management plan.
Correct answer: D
Explanation
The correct answer is D, as reviewing the communications management plan will help ensure effective information dissemination among team members, reducing the likelihood of missed communications. The other options focus on different aspects of project management that do not specifically address the communication issues leading to the delay.