Project Management Professional (PMP) — Question 407

An oil and gas project started without having acquired full funding for the project. The remaining funds were to be acquired during project execution. The acquisition of the remaining funds was delayed several months, resulting in a suspension of work by all contractors.
What should the project manager have done to prevent this from happening?

Answer options

Correct answer: B

Explanation

The correct answer is B because adequately assessing and mitigating risks is crucial in project management, especially regarding funding. Options A, C, and D do not address the fundamental issue of risk assessment and mitigation, which directly affects the project's ability to secure necessary funding and continue operations.