Project Management Professional (PMP) — Question 394
A project manager is working on an enterprise resource planning (ERP) implementation project that spans divisions within and outside the country. The project manager understands the importance of gate reviews and periodic checks.
Which of the following should the project manager leverage?
Answer options
- A. Project management plan
- B. Governance framework
- C. Integration plan
- D. Project management office (PMO)
Correct answer: B
Explanation
The correct answer is B, the Governance framework, as it provides the necessary structure and guidelines for overseeing the project and ensuring compliance with organizational policies. The other options, while important, do not specifically focus on the oversight and control aspects that a governance framework offers.