Project Management Professional (PMP) — Question 374
A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client.
How should the project manager proceed?
Answer options
- A. Update the quality management plan for the overall project
- B. Ask the client to verify and accept the tasks that have been completed
- C. Close out the project tasks that have been completed
- D. Update the communications management plan for the overall project
Correct answer: B
Explanation
The correct answer is B, as it ensures that the client acknowledges and accepts the completed tasks, which is crucial for project closure. Options A and D are not immediately relevant to the handover process, and C, while it implies completion, does not involve client verification which is essential in this context.