Project Management Professional (PMP) — Question 375

A project manager has been assigned to a project after the charter has been approved. While reviewing the charter with the team, the project manager finds that some major budget items, necessary for achieving the project outcome, have been missed.
What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because it is essential for the project manager to communicate with the project sponsor to address any budget discrepancies immediately and ensure the project's financial foundation is solid. Options B and D are inadequate as they do not address the urgency of the missing budget items, and option C is risky as it suggests proceeding with known budget issues that could jeopardize the project's success.