Project Management Professional (PMP) — Question 371
Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.
What should the project manager do next to address this issue?
Answer options
- A. Obtain and implement the sponsor's recommendations for a solution.
- B. Ask the team members to proceed independently while examining needs and alternatives.
- C. Place a hold on activities until the team can resume the work on-site.
- D. Halt all processes until procurement and implementation of solutions are completed.
Correct answer: B
Explanation
The correct answer is B because allowing team members to work independently while assessing their needs encourages flexibility and productivity despite the travel restrictions. Option A may delay action by relying on the sponsor's input, while Option C halts progress altogether, and Option D unnecessarily stops all operations, which could lead to project delays.