Project Management Professional (PMP) — Question 371

Travel restrictions are suddenly imposed during a project's execution. The team members reside in different geographic locations.

What should the project manager do next to address this issue?

Answer options

Correct answer: B

Explanation

The correct answer is B because allowing team members to work independently while assessing their needs encourages flexibility and productivity despite the travel restrictions. Option A may delay action by relying on the sponsor's input, while Option C halts progress altogether, and Option D unnecessarily stops all operations, which could lead to project delays.