During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?

Answer options

Correct answer: C

Explanation

The correct answer is C because submitting a change request is the appropriate first step to formally document the client's desire to accelerate the project. Options A and B do not address the immediate need to respond to the client's request, while option D is premature as it seeks funding without first assessing the need for a change request.