Project Management Professional (PMP) — Question 369
A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?
Answer options
- A. Invite the Scrum team members as optional participants.
- B. Ask the Scrum team members to share retrospectives.
- C. Invite the Scrum team members as mandatory participants.
- D. Ask the scrum master to attend the workshops.
Correct answer: C
Explanation
The correct answer is C, as involving the Scrum team is crucial for gathering insights and feedback that can help improve future projects, regardless of the current project's success. Options A and D undermine the importance of the Scrum team's contributions by making their attendance optional or limited to just the scrum master. Option B, while beneficial, does not ensure the entire team is present to engage in discussions and share lessons learned collectively.