Project Management Professional (PMP) — Question 340

After sending an on-site meeting invitation to seven people for the kick-off meeting of a project, a key stakeholder declines because they will be at another location for the rest of the month.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it allows the key stakeholder to participate in the meeting despite their absence. Option A is incorrect as it does not specifically address the stakeholder's situation. Option B is not ideal since it excludes a key participant, and Option C delays the project unnecessarily.