Project Management Professional (PMP) — Question 337

A team has been working for some time on a project with incremental deliveries. The project manager noticed that one of the team members is less engaged in team meetings, yet delivers promptly. While discussing the source of demotivation, the team member informed the project manager that this is due to a feeling of lack of skills in dealing with new tasks.
How should the project manager address the issue?

Answer options

Correct answer: C

Explanation

The correct answer is C because discussing growth and development needs allows the project manager to understand the team member's challenges and provide targeted support. Options A and B do not address the root cause of the demotivation, which is the team member's confidence and skill gap. Option D, while helpful, may not provide the direct support needed to enhance the team member’s skills in a structured manner.