Project Management Professional (PMP) — Question 327

A project manager has been using predictive methodology for more than 10 years and is switching to an agile project. The team members have not previously worked together. After two sprints of work, the team has not achieved any outcome and there is a lot of pressure to get work done.
What kind of leadership style should the project manager use at this stage?

Answer options

Correct answer: B

Explanation

The correct answer is B because coaching and fostering collaboration will help the team build trust and improve their performance in an agile environment. Options A and D may impose decisions or majority rule, which can hinder team dynamics and creativity, while option C's passive approach may not provide the necessary guidance during the initial stages of team formation.