Project Management Professional (PMP) — Question 328

A project manager is leading an electrical project that spans five towns. The project manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because engaging with the town's authorities allows the project manager to understand the situation better and work towards a viable solution. Option B risks project continuity without addressing the underlying issue, C could lead to project scope complications, and D may appear confrontational rather than collaborative, potentially worsening relations with the town.