Project Management Professional (PMP) — Question 297

A project manager is working on an agile project that is within the scope of a recently announced corporate audit. The project manager was appointed to attend the first meeting with the auditors scheduled for the following week.
What should the project manager do to prepare for the audit?

Answer options

Correct answer: B

Explanation

The correct answer is B, as reviewing the project information is essential for understanding the project's status and ensuring compliance during the audit. Options A and C are not directly related to preparing for the audit, and D is inappropriate as seeking a waiver does not align with audit preparation.