As part of a company's planning effort for team capacity building, the project manager was asked to provide management with a list of required trainings for the project team.

What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because it emphasizes identifying gaps in competencies specifically related to the project pipeline, ensuring that the trainings align with the project needs. Options A and B focus on performance and team meetings rather than directly on the gaps within the project pipeline, while option D lacks the broader perspective of project execution requirements.