Project Management Professional (PMP) — Question 298
As part of a company's planning effort for team capacity building, the project manager was asked to provide management with a list of required trainings for the project team.
What should the project manager do?
Answer options
- A. Review the gaps found during project execution, prepare a list of recommended trainings, and discuss it during a team meeting.
- B. Review the project schedule and the team members' performance, and decide on soft skills and related trainings needed for the team.
- C. Review the project pipeline, identify gaps in competencies for execution, and decide on the needed trainings.
- D. Review the team members' latest performance, identify gaps in competencies, and decide on the needed trainings.
Correct answer: C
Explanation
The correct answer is C because it emphasizes identifying gaps in competencies specifically related to the project pipeline, ensuring that the trainings align with the project needs. Options A and B focus on performance and team meetings rather than directly on the gaps within the project pipeline, while option D lacks the broader perspective of project execution requirements.