Project Management Professional (PMP) — Question 275

A project manager starts to receive emails from different stakeholders requesting information about the project status.
What should the project manager do to avoid this in the future?

Answer options

Correct answer: B

Explanation

The correct answer is B because addressing stakeholder needs in the communication strategy during planning helps establish a clear and proactive communication plan. Options A and C are reactive solutions that don't prevent future inquiries, while option D may overwhelm stakeholders with information instead of providing structured updates.