Project Management Professional (PMP) — Question 273

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.
Which action should the project manager take to address the sponsor's request?

Answer options

Correct answer: A

Explanation

Option A is correct because collaborating with the legal department ensures that the project complies with local laws, thereby minimizing potential issues with the local government. The other options, while relevant to the store's opening, do not directly address the sponsor's concern about compliance with local regulations.