As a member of an organizational change management team, a project manager must pass on any changes to the project team. The project manager needs to avoid any misunderstandings or resistance to help ensure that the project team will support any organizational change.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because regular meetings keep the project team informed and engaged, reducing the chance of misunderstandings. Option A addresses resistant members but does not ensure overall team awareness, while C focuses on influencing communication rather than proactive updates. Option D checks willingness but lacks the proactive approach needed to keep the entire team informed.