An experienced, high-performing team has two new team members. After several iterations with the new team members, the project manager noticed that the team's performance has decreased.

What should the project manager do?

Answer options

Correct answer: C

Explanation

Providing the team with a coaching session can help integrate the new members effectively, enhancing overall performance. Evaluating or replacing the new members may not address the underlying issues, while allowing self-organization might not provide the necessary guidance to improve team dynamics.