Project Management Professional (PMP) — Question 259

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages. The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope.
What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A, as it emphasizes the need for the project manager to communicate the importance of consistency in the sprint cycle to the sponsor. This helps ensure that the team can work effectively without constant changes. Options B and C do not address the root cause of the issue, while option D shifts the methodology rather than addressing the sponsor's behavior.