Project Management Professional (PMP) — Question 237

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried to contact the consultant but has been told that the consultant does not have the time to discuss the project.
What should the project manager do to move the project forward?

Answer options

Correct answer: C

Explanation

The correct answer is C because setting up a direct discussion between the business analyst and the consultant facilitates collaboration and ensures project requirements are addressed. Options A and B suggest escalating or assigning blame, which does not resolve the immediate issue, while option D merely encourages continued attempts without providing a solution.