Project Management Professional (PMP) — Question 238

The project manager just started leading a project team from which the previous project manager resigned. After a quick evaluation of the project, it is apparent that team morale is low due to continuous disagreement about how to complete tasks. Tasks are taking longer than forecasted and the project is off schedule.
What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because addressing the sources of disagreement directly with the team can help improve morale and collaboration, which are crucial for project success. Options B, C, and D do not tackle the underlying issue of team conflict and may worsen the situation by either pushing for unrealistic timelines or shifting blame without resolving the core problems.