Project Management Professional (PMP) — Question 214

A project manager holds periodic progress review meetings to discuss issues.

What should the project manager do first on the agenda?

Answer options

Correct answer: B

Explanation

The correct answer is B because updating resolution approaches and action assignments is crucial for addressing current issues effectively. Options A, C, and D, while important, are not the immediate priority when focusing on resolving ongoing challenges that arise during the project's progress.