Project Management Professional (PMP) — Question 203
A project is 70% complete when the project sponsor requests an additional deliverable.
What should the project manager do first?
Answer options
- A. Negotiate with the project sponsor on the possible alternatives
- B. Determine the possible impact of this change on all aspects of the project
- C. Reject the request as being too late and leading to major scope creep
- D. Submit the request to the change control board (CCB) for a decision
Correct answer: B
Explanation
The correct answer is B because understanding the impact of the change is crucial before taking further action. Options A and D may be steps taken later, but they rely on knowing the implications first. Option C is not advisable as it dismisses the sponsor's request without evaluating the potential effects.