Project Management Professional (PMP) — Question 202

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the quality standards required by regulations.
What should the project manager have done to avoid this?

Answer options

Correct answer: C

Explanation

The correct answer, C, is crucial because reviewing acceptance criteria ensures that the features align with the stakeholder's quality expectations before presentation. Option A focuses on scope awareness, which does not directly address quality concerns. Option B is about addressing concerns post-iteration, which is too late to prevent rejection. Option D pertains to backlog management rather than quality assurance of completed stories.