Project Management Professional (PMP) — Question 201

A new major road project is starting, and the contractor has contractually committed to submitting regular status reports and participating in integration meetings.
Halfway through the project life cycle, the contractor stops participating in meetings and submitting reports, stating these items consume too much time.
What should the project manager do first?

Answer options

Correct answer: B

Explanation

The correct answer is B because it directly addresses the contractor's non-compliance by reminding them of their contractual commitments. Options A, C, and D are more reactive and do not immediately resolve the issue, potentially allowing the problem to persist without addressing the contractor's responsibilities.