Project Management Professional (PMP) — Question 193

A project manager works in a hierarchical organization. The project team members are used to being told what to do, and the performance reviews include the percentage of completion of the allocated tasks. After a conversation with the sponsor, the project manager realizes that they need to reassign a couple of tasks to meet the next milestone. This change can be perceived as poor performance by the current assignees.
What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it involves transparent communication and collaboration with the team, which is essential in a hierarchical environment. This approach helps mitigate any potential negative perceptions regarding task reassignment. The other options lack team involvement and may lead to dissatisfaction and confusion among team members.