Project Management Professional (PMP) — Question 192
A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with another team to ensure the continuity of deliverables.
What should the project manager do?
Answer options
- A. Remove the dependency to eliminate the need for knowledge sharing.
- B. Redistribute the team members so knowledge is available in both teams.
- C. Merge both teams into one team so the knowledge is commonly available.
- D. Request the respective teams to plan for knowledge-sharing sessions.
Correct answer: D
Explanation
The correct answer is D because planning knowledge-sharing sessions directly addresses the need for collaboration and ensures that both teams can continue delivering effectively. Options A, B, and C do not facilitate the necessary sharing of knowledge and may hinder project progress by either ignoring the dependency or restructuring teams unnecessarily.