A project manager is working on a large IT project. During a review for one of the deliverables. a stakeholder raised a concern about the final product.
What should the project manager do first?
Answer options
- A. Discuss this with the team and put the stakeholder's concern in the issue log.
- B. Set up a meeting with the sponsor to discuss the details of the deliverable.
- C. Discuss this with the team and review the project requirements documentation.
- D. Set up a meeting with the product owner to discuss the stakeholder's concern.
Correct answer: C
Explanation
The correct answer is C because the project manager needs to clarify the project's requirements with the team to understand the stakeholder's concern better. Options A and D focus on external discussions rather than addressing the core issue with the project details, while option B involves the sponsor, which may not be necessary at this stage.