Project Management Professional (PMP) — Question 186

A company is implementing a project with team members located in different countries and time zones. Individual performance is satisfactory, but the team's performance as a whole is low, especially in terms of group activities.
What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because enhancing communication and fostering teamwork are essential for improving collaboration in a geographically dispersed team. Reviewing assignments (A) may not address the core issue of communication, negotiating for new members (C) could complicate team dynamics, and simply updating the communications plan (D) does not actively promote team engagement.