Project Management Professional (PMP) — Question 153
A project manager is working on a complex project with a high degree of change.
What strategy should the project manager use to ensure a successful project completion?
Answer options
- A. Update the project management plan to reduce the possibility of scope creep.
- B. Schedule a regular risk review with the project management team.
- C. Increase the active engagement and participation of key stakeholders.
- D. Create a project change roadmap to keep track of all unforeseen changes.
Correct answer: C
Explanation
The correct answer, C, emphasizes the importance of actively involving key stakeholders, which can lead to better communication and support throughout the project. Options A and D focus on managing changes but do not prioritize stakeholder engagement, while B, although valuable, does not directly address the need for stakeholder involvement in a change-heavy environment.