Project Management Professional (PMP) — Question 152

A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.
What should the project manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because analyzing and interpreting the data is essential for providing meaningful insights in the report. Option A does not prioritize the analysis of data, while option B limits the presentation to graphics, and option C may be premature without first understanding the data.