Project Management Professional (PMP) — Question 152
A project team is preparing a report for the stakeholders. The team gathers and collates a large amount of data to be included in the status report.
What should the project manager do next?
Answer options
- A. Ensure the team follows standard operating procedures (SOP) for creating a stakeholder report.
- B. Instruct the team to make only a graphical representation of all the data for the report.
- C. Instruct the team to conduct a meeting with the stakeholders before finalizing the report.
- D. Instruct the team to analyze and interpret the data before including it in the report.
Correct answer: D
Explanation
The correct answer is D because analyzing and interpreting the data is essential for providing meaningful insights in the report. Option A does not prioritize the analysis of data, while option B limits the presentation to graphics, and option C may be premature without first understanding the data.