Project Management Professional (PMP) — Question 1394

In a project that will deliver a new product using new technology, the project team frequently discusses difficulties that may arise and possible strategies to address them. One team member sets up a meeting with the project manager to discuss their list of challenges and presents an extensive list of items that require continuous attention.

How should the project manager use this event to maximize the benefits to the stakeholders?

Answer options

Correct answer: A

Explanation

The project manager should validate the list of challenges and prioritize the valid items to ensure that the most critical issues are addressed first, maximizing stakeholder benefits. Documenting findings (B) and inviting participation in the risk register (C) are important, but without prioritization, they may not effectively address the most urgent challenges. Presenting to the steering committee (D) does not directly resolve the challenges but seeks approval instead of taking actionable steps.