Project Management Professional (PMP) — Question 1391

A project manager is in a team meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change. What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because scheduling a project decision meeting with all stakeholders ensures that everyone affected by the timeline change can provide input, leading to a more informed decision. Option A does not directly address the need for a decision, option B may delay the process by requiring delegation, and option D could overlook valuable stakeholder perspectives.