Project Management Professional (PMP) — Question 1390

A customer calls the project manager to express concern about a project team member who has been making changes within the live environment without approval. The team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because it emphasizes the necessity of following proper procedures for change requests, which helps maintain project integrity. Options A and B do not address the underlying issue of unauthorized changes, while option C may not ensure accountability for future requests.