A project is starting its sixth iteration out seven. During the daily meeting, a team member explains that a key function will take longer to complete than originally anticipated.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because it involves collaborating with the team to explore solutions and adjustments that may help to meet project goals. Options A and B may not address the issue directly or could lead to additional delays, while option C, while important for documentation, does not actively seek to resolve the problem at hand.