Project Management Professional (PMP) — Question 1332

A member of the project team always extends discussion topics, taking more time than necessary during project team meetings. Other team members feel this member is not being considerate of their time.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because it emphasizes the importance of open discussions while reinforcing the need to adhere to ground rules, which helps maintain meeting efficiency. Option B is too restrictive and could stifle valuable input, while option C encourages unfiltered contributions without addressing the time management issue. Option D may not provide a timely resolution to the ongoing concern.