Project Management Professional (PMP) — Question 1333
A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the complexity of the work was underestimated.
What should the project manager do?
Answer options
- A. Update the issue log and escalate it to the project sponsor.
- B. Ask the technical manager to help the team with the issue.
- C. Meet with the team to review internal actions to resolve the situation.
- D. Ask to replace some team members with more experienced ones.
Correct answer: C
Explanation
The correct answer is C because meeting with the team allows for collaboration to identify practical solutions and improve future iterations. Option A does not directly address the issue, while B may not be necessary if the team can resolve it internally. Option D could disrupt team dynamics and may not be the best approach to enhance performance.