Project Management Professional (PMP) — Question 1331

A project manager is planning a project with multiple work packages. Each work package has its own defined scope, but funding will be at the project level.
How should the project manager determine if the allocated resource budget is sufficient to cover the resource costs of the project?

Answer options

Correct answer: A

Explanation

The correct answer is A because it involves estimating costs for each work package, summing them to establish a total project cost, and then comparing that to the overall budget. Options B, C, and D do not provide a comprehensive method for determining the sufficiency of the budget against the total cost of all work packages.