Project Management Professional (PMP) — Question 1319

A company is engaged in a transformation journey, and the project manager for this endeavor is new to this project. During one of the project status update meetings, a key stakeholder, the project manager's functional manager, is dissatisfied with the work in progress, and points to the project manager.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D, as it emphasizes the importance of active listening and understanding stakeholder concerns, which can build trust and rapport. Options A and C focus on proving progress rather than addressing the stakeholder's concerns, while option B prematurely admits fault without seeking to understand the underlying issues.