The project manager of a high-risk project is concerned about a delay in the schedule that might force the project to move its go-live date. What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because capturing the risk in the risk register allows for proactive management and monitoring, which is essential for high-risk projects. Option B is incorrect as it focuses on additional funding rather than addressing the risk directly. Option C overlooks the importance of risk management in favor of merely adhering to timelines, while D proposes a new project instead of managing the current risk.