A project manager is using an agile approach. During the sprint planning meeting, the product owner flagged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is flagged as low business value and high complexity.

What should the project manager do to support the backlog prioritization?

Answer options

Correct answer: C

Explanation

The correct answer is C because facilitating a discussion allows the team to collaboratively evaluate the dependencies and business values of the items, leading to a more informed decision. Options A and B do not address the dependency issue and may lead to complications, while D prioritizes an item with low business value, which is not aligned with the goal of maximizing business value.