Project Management Professional (PMP) — Question 1270
A project manager is assigned to a project that will improve the business operations for a trading firm. The project team has just completed the discovery phase and needs to make a presentation to the business team in 4 weeks to showcase the feasibility of the solution.
How should the project manager advise the team to proceed?
Answer options
- A. Develop a conceptual framework.
- B. Develop a request for proposal (RFP).
- C. Develop a prototype.
- D. Develop a minimum viable product (MVP).
Correct answer: C
Explanation
The correct answer is C, to develop a prototype, as it allows the team to create a tangible representation of the solution, making it easier to demonstrate feasibility to stakeholders. Options A and B are more about planning and documentation rather than providing a demonstration of the solution, while option D, developing a minimum viable product, is more advanced and not suitable at this stage of showcasing feasibility.