Project Management Professional (PMP) — Question 1269

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client. A potential design problem is identified by the development team. After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed. The design is already approved.
What should be the project manager's next steps?

Answer options

Correct answer: C

Explanation

The correct answer is C because conducting a proof of concept allows the team to validate that the revised design effectively resolves the identified issue before full implementation. Options A and B involve processes that could delay necessary changes, and option D skips critical validation steps before reprogramming the system.