Project Management Professional (PMP) — Question 127
A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.
Which measure should mitigate the impact of this key resource's departure?
Answer options
- A. Establish a proactive knowledge-sharing plan
- B. Offer a new contract to the resource who is leaving
- C. Develop a contingency budget to replace the key resource
- D. Update the risk register and inform the customer
Correct answer: A
Explanation
The correct answer is A because establishing a proactive knowledge-sharing plan ensures that the departing resource's knowledge is transferred to the remaining team members, minimizing disruption. Offering a new contract (B) is unlikely to retain the resource if they have already decided to leave. Developing a contingency budget (C) does not address the immediate knowledge gap, and updating the risk register (D) is necessary but does not directly mitigate the impact of losing the resource.