Project Management Professional (PMP) — Question 126
In the initiating phase of a project, the project manager and team members are prioritizing the product backlog along with the product owner.
What should the project manager do next?
Answer options
- A. Produce a value-added product for the customer in each phase of the project.
- B. Produce a value-added product for the customer as continuously as possible.
- C. Produce a value-added product for the customer in the beginning of the project.
- D. Produce a value-added product along with the supporting documentation.
Correct answer: B
Explanation
The correct answer is B because it emphasizes the importance of delivering value to the customer as often as possible, aligning with agile principles. Options A, C, and D focus on specific phases or additional documentation, which do not prioritize continuous delivery of value.