Project Management Professional (PMP) — Question 128

The project manager of an agile project has been asked to reduce the budget by 30%. Since this is a small project team, the budget is primarily allocated to resources.
What strategy should the project manager use in order to keep delivering value in a restricted environment?

Answer options

Correct answer: C

Explanation

The correct answer is C because prioritizing the product backlog allows the team to focus on delivering the most valuable features while effectively managing the reduced budget. Options A and B do not prioritize value delivery as effectively, and option D risks delivering less value by constraining scope without leveraging high-value tasks.