Project Management Professional (PMP) — Question 1256

A project team has run into an issue with a vendor who is known for a lack of quality. The project manager must ensure that the quality problem is addressed appropriately.

What should the project manager do to start the issue resolution process?

Answer options

Correct answer: C

Explanation

The correct answer is C because reviewing the risk register allows the project manager to assess the quality issue's impact and implement an appropriate response strategy. Options A and B focus on immediate actions without considering the broader risk management framework, while option D suggests documentation but does not initiate a proactive resolution process.