Project Management Professional (PMP) — Question 1257

A human resources (HR) cost report was disclosed, by error, to all members of the project team. This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

Answer options

Correct answer: C

Explanation

The correct answer is C because defining the appropriate recipients in the communications management plan would directly prevent unauthorized access to sensitive information. Options A and B do not address the issue of recipient management, while D, although related, focuses more on validation rather than ensuring the right recipients are designated.